Metro Water District

Capital Improvements and Projects

Capital Improvement Overview – During its first two decades, the District actively constructed and upgraded critical infrastructure to ensure the reliability of its water system. The biggest challenge facing water utilities now and into the future is the need to replace aging infrastructure, which is projected to cost billions throughout the United States. Since the District has been proactive through two Capital Improvement Programs (CIP), the District has minimized significantly the risk of aging infrastructure and reduced overall costs for the future through various improvements.
 
1st Five-Year Capital Improvement Program – On March 11, 1997, a 79% voter approval gave the green light to the District's $23 million CIP to address deficiencies identified in the 1994 Water System Management Plan. The District issued $13 million in Water Revenue Bonds in 1999 with the remaining $10 million bonds issued as part of the Series 2002 Bonds. A Bond Oversight Committee, now known as the Finance Oversight Committee, has actively watched over the CIP to ensure the funding was spent as the voters agreed.
 
2nd 10-Year Capital Improvement Program – In August 2004, the Board approved a second 10-year Capital Improvement Program to continue to upgrade Metro's service areas. While the 1st 5-year CIP greatly improved Metro's overall system, it was recognized that further improvements were necessary to meet present and future water demands.
 
In October 2004, the Board called for a bond election to finance the first phase of the 10-year CIP. In March 2005, 83 percent of those who voted approved the $28 million bond. Subsequently, the District obtained a loan agreement from the Water Infrastructure Financing Authority of Arizona for $15.375 million in October 2005 for the design and construction of six major capital projects with funds expended by October 2008 for this phase of the 10-year Capital Improvement Program. On November 9, 2007, the Water Infrastructure Financing Authority of Arizona approved the second phase of the $28 million Capital Improvement Program with a loan in the amount of $12.625 million dollars.
 
In October 2008, the Board decided not to pursue another bond election due to the financial uncertainties of the overall economy.
 
To date, the District has installed over 100,000 linear feet of transmission mains, replaced approximately 150,000 linear feet of aged and undersized waterlines in neighborhoods and other locations, installed and improved water supply wells and pumping facilities, installed auxiliary power, and completed construction of over 10 million gallons water storage facilities.

Future Capital Improvements – The District routinely identifies capital projects that will continue to improve the water system. The District funds the annual CIP through its priority driven budget.


 Completed Projects

Northeast Reservoir
Northeast Reservoir Booster Facility
Magee Road Transmission Main, Phase 3
Paseo del Norte ‘C' Zone Transmission Main
Village Avenue ‘C'/'D' Zone Transmission Main
La Cañada Drive ‘C' Zone Transmission Main
Hub Storage Expansion
Mainline Replacement Program
Lomas de Oro Wash Improvements
La Cañada Drive - Ina Road to Calle Concordia
(RTA)
Magee Road - Shannon Road to La Cañada Drive (RTA)
Magee Trail Well Drilling
Shannon Road Transmission Main (portion within RTA project)
La Cañada Drive ‘A' Zone Transmission Main
Magee Trail Well Improvements
Cortaro Farms Road/Magee Road Reclaimed Water Line
La Cañada Drive - River Road to Ina Road (RTA)
Magee/Cortaro Farms Road - Thornydale Road to Shannon Road (RTA)
La Cholla Boulevard - Magee Road to Overton Road (RTA)
Riverside Well Transmission Main
Riverside Well Improvements

Current Projects
Metro-HUB Well Site #1A Improvements

Future Projects
Shannon Road Transmission Main (remainder outside RTA project)
CAP Recharge and Recovery System

Pima County/RTA Roadway Projects (with Associated Water Line Relocations)
La Cañada Drive - Ina Road to Calle Concordia
La Cañada Drive - River Road to Ina Road
Magee Road - Shannon Road to La Cañada Drive
Magee/Cortaro Farms Road - Thornydale Road to Shannon Road
Magee Road - La Cañada Drive to Oracle Road
La Cholla Boulevard - Magee Road to Overton Road
Orange Grove Road - Camino de la Tierra to La Cholla Boulevard
Orange Grove Road - Via Ranchero to Willowhaven Drive
Ina/Oracle Intersection Improvements

Project Descriptions

James M Tripp (Northeast) Reservoir
Construction of a 5 million gallon reservoir, located in the area of Magee Road and 1st Avenue, to serve the water storage needs for the northeast ‘B', ‘C' and ‘D' Zone service areas.

Northeast Reservoir Booster Facility
Construction of new booster facility, located at the intersection of Magee Road and Leonardo da Vinci Way, that pumps up to 5 million gallons per day from the ‘A' Zone system to the Northeast Reservoir located in the ‘E' Zone (‘D' Zone gravity feed).

Magee Road Transmission Main, Phase 3
Final leg of the transmission main system connecting to the Northeast Reservoir down Magee Road, from Northern Avenue to 1st Avenue.

Paseo Del Norte ‘C' Zone Transmission Main
First of three transmission main projects to connect the Magee Road Transmission Main to the existing distribution system, in Paseo del Norte from Magee Road to Ina Road.

Back to top

Village Avenue ‘C'/'D' Zone Transmission Main
Second of three transmission main project to connect the Magee Road Transmission Main to the existing distribution system in Village Avenue.

La Cañada Drive ‘C' Zone Transmission Main
Third of three transmission main projects to connect the Magee Road Transmission Main to the existing distribution system, and also serve as the first leg of a transmission main to connect the upper northwest and upper northeast service areas/zones.

Hub Storage Expansion
A 250,000 gallon storage expansion, and planning for one million gallons total, to provide build-out storage needs for the Metro-Hub service area.

Mainline Replacement Program
The mainline replacement/fire hydrant program exists to replace undersized and old distribution piping in various neighborhoods across the District, as well as provide additional fire protection for Metro Water customers. Several mainline replacement/fire hydrant projects were completed during the second capital improvement program within the Metro-Main and Metro-Hub service areas, though some needed to be postponed due to District obligations for waterline relocations on RTA roadway projects. In addition, several transmission main projects needed to be expedited so construction could occur in advance of the new roadways (that have also been expedited). Additional mainline replacement areas will be completed as funding becomes available.

Lomas De Oro Wash Improvements
Improvement of the Lomas de Oro Wash by the Town of Oro Valley from just south of Lucero Road, north through several private properties, including associated utility relocations.

Back to top

Shannon Road Transmission Main
Designed to deliver water from the Linda Vista Boulevard Transmission Main to the existing ‘A' Zone transmission main system at Magee Road/Cortaro Farms Road, including crossing the Cañada del Oro Wash.  A portion constructed as part of the waterline relocation plans for the Magee Road/Cortaro Farms Road - Thornydale to Shannon roadway improvements for the RTA.  The remainder of this transmission main north of this project will be constructed under a different funding source.

La Cañada Drive ‘A' Zone Transmission Main
Designed to extend the ‘A' Zone transmission system in La Cañada Drive, from Orange Grove Road to Roller Coaster Road. This transmission main project will be constructed as part of the La Cañada Drive - River Road to Ina Road roadway improvements for the RTA.

Riverside Well Transmission Main
Designed to connect the Riverside Well to the ‘A' Zone transmission system, primarily in Roller Coaster Road, from La Cañada Drive through to River Road.

Riverside Well Improvements
Equips the Riverside Well along River Road to serve in a municipal capacity, pumping into the ‘A' Zone transmission system.

Back to top

CAP Recharge and Recovery System
As Metro Water continues to recharge Central Arizona Project (CAP) water at the Avra Valley Recharge Facility (since 1996), this project is to plan, design, and construct a recovery and delivery system for recharged CAP water to serve the entire Metro-Main service area, including recovery wells, transmission pipelines, storage and booster facilities, and potential water treatment.

Magee Trail Well Drilling
Drilling and developing a municipal well just east of the intersection of La Cholla Boulevard and Magee Road (north leg), and is a replacement well for the Matter Well within La Cholla Boulevard right-of-way, abandoned as part of theLa Cholla Boulevard - Magee Road to Overton Road roadway improvements.

Magee Trail Well Site Improvements
Equips the Magee Trail Well to serve in a municipal capacity, pumping into the 'A' Zone transmission system.

Cortaro Farms Road/Magee Road Reclaimed Water Line
Construction of a reclaimed water line in Cortaro Farms Road/Magee Road, from the Tucson Water interconnect (just east of Thornydale Road) to the CDO bridge, and done concurrently with Cortaro Farms Road/Magee Road - Thornydale Road to Shannon Road roadway improvements with the RTA.

Metro-HUB Well Site #1A Improvements
Equips Hub Well No. 1A, just south of Fruchthendler Elementary School on the SW corner of Cloud Road and Lodge Road, to serve in a municipal capacity, and replaces Metro-HUB Well Site No. 1.

Back to top

RTA/Pima County Roadway Project Descriptions

La Cañada Drive - Ina Road To Calle Concordia (Concurrent With La Cañada Drive ‘C' Zone Transmission Main)
Pima County/RTA roadway project involving a four-lane divided roadway section with multi-use lanes, medians, drainage improvements, sidewalks, etc., along with associated utility relocations, and constructed concurrently with the La Cañada Drive ‘C' Zone Transmission Main.

La Cañada Drive - River Road To Ina Road (Concurrent With La Cañada Drive ‘A' Zone Transmission Main)
Pima County/RTA roadway project that continues the north segment from Ina Road to River Road, involving a four-lane divided roadway section, multi-use lanes, medians, drainage improvements, sidewalks, etc., along with associated utility relocations, and constructed concurrently with the La Cañada Drive ‘A' Zone Transmission Main from Orange Grove Road to Roller Coaster Road.

Magee Road - Shannon Road To La Cañada Drive
Pima County/RTA roadway project and first of three phases to expand the entire corridor of Cortaro Farms Road/Magee Road from Thornydale Road to Oracle Road to a 4-lane divided roadway section, with multi-use lanes, medians, drainage improvements, etc., along with associated utility relocations, and including a major reconfiguration/realignment of the La Cholla Boulevard/Magee Road intersection.

Magee/Cortaro Farms Road - Thornydale Road To Shannon Road (Concurrent With The Shannon Road Transmission Main-Phase I, And The Cortaro Farms Road/Magee Road Reclaimed Water Line)
Pima County/RTA roadway project and second of the three phases to expand the entire corridor of Cortaro Farms Road/Magee Road from Thornydale Road to Oracle Road to a 4-lane divided roadway section, with multi-use lanes, medians, drainage improvements, etc., along with associated utility relocations, including an additional bridge across the CDO wash, and concurrent construction of the Shannon Road Transmission Main-Phase I and the Cortaro Farms Road/Magee Road Reclaimed Water Line.

Magee Road - La Cañada Drive To Oracle Road
Pima County/RTA roadway project and third of the three phases to expand the entire corridor of Cortaro Farms Road/Magee Road from Thornydale Road to Oracle Road to a 4-lane divided roadway section, with multi-use lanes, medians, drainage improvements, etc., along with associated utility relocations.

La Cholla Boulevard - Magee Road To Overton Road
Pima County/RTA roadway project, continuing the improvements at the Magee Road/La Cholla Boulevard intersection, and expanding this corridor to a 4-lane divided roadway section, with multi-use lanes, medians, drainage improvements, etc., along with associated utility relocations, and including a new bridge over the CDO Wash (just south of Overton Road).

Orange Grove Road - Camino de la Tierra to La Cholla Boulevard
Pima County roadway improvement project to expand the existing 3-lane roadway section to a 5-lane roadway section with a center 2-way turn lane, bike lanes, and drainage improvements, along with the associated utility relocations.

Orange Grove Road - Via Ranchero to Willowhaven Drive
Pima County roadway improvement project to expand the existing 2-lane roadway section to add a center 2-way turn lane, right-turn lanes, and bike lanes, along with the associated utility relocations.

Ina/Oracle Intersection Improvements
Pima County intersection improvement project to reconfigure the management of traffic, reduce congestion, and improve drainage, along with the associated utility relocations.

Back to top

H2Know:

Metro Water increased its storage capacity of 4.5 million gallons in 1992 to over 16.5 million gallons in 2008. More storage increases overall reliability... More>

  • © Metropolitan Domestic Water Improvement District
  • 6265 N. La Cañada, Tucson, Arizona 85704
  • 520-575-8100 (office)
  • 520-575-8454 (fax)

Office hours: Monday – Thursday 7:30am - 5:30pm and Friday 7:30am - 12 noon